Feasibility Study, Preliminary and Detailed Design for Integrated Water Supply in Bidibidi Settlement and Neighboring Host Community in Yumbe District Lot 1

×

Error message

Deprecated function: Optional parameter $conditions declared before required parameter $data is implicitly treated as a required parameter in include_once() (line 1439 of /home/barow6bcmdg2/public_html/gauff/includes/bootstrap.inc).

Client

financier

Project description
Project scope

The main objective of this study is to formulate a comprehensive and sustainable water supply system(s) layout/master plan for Bidibidi Refugee Settlement and the neighboring host communities in Yumbe.

IWRM principles are to be considered in the development of this system. The project includes feasibility study, preliminary and detailed design with the aim of proposing an integrated water supply system(s) for Bidi Bidi and neighboring host communities. The proposed system shall meet mid to long term demands for water.

The study also considered works/recommendations from previous studies already undertaken in the settlements that can be utilized in meeting this demand.

Stage-I: Feasibility Study Report & Preliminary Design for water supply system for 25-year horizon

Stage-II: Detailed design for the water supply system including Construction Packaging

  • Surface water assessment and Ground water assessment.
  • Design of water transmission and distribution network to cover the settlement and the host communities within a radius not exceeding 20km from the refugee settlement.
  • Generation of a hydrogeological map and the inferred groundwater flow of the target area 
  • Identification and mapping of locations that are vulnerable to any form of threats and propose mitigation measures that can be undertaken to either eliminate or control/manage the threats to the resource. 
  • Confirmation of the existing settlements’ water supply boreholes and quality of service, capacities, water quality, location of wells for both the refugee settlements and host community, reservoirs, pumping stations and transmission mains in settlements and neighbouring community. 
  • Compilation of reports presenting different water supply options including advantages and disadvantages, cost estimate, schematic design, sustainability solutions including Operation & maintenance that consider financial/economic considerations, technical requirements, institutional requirements, capacity requirements etc, and recommendations on the most feasible and technically sound option. 
  • Detailed engineering design (calculations, drawings, specifications of all components and facilities of the integrated water supply system including rehabilitation of existing ones and development of new ones) , storage (and or similar arrangements including the rehabilitation of existing ones , if any or the design of new storage facilities), network.
  • Preparation of tender documents for the construction of the works.
category
Sector
Water and Environment
map
Location
Yumbe
schedule
Duration
May 2018 to October 2018

More Projects